Construction of Flood Mitigation Structure23OD0140

Construction of Flood Control Structure along the Banks of Creeks along Kabatuhan Rd., Barangay 168, Caloocan City (Phase 3)

Construction of Flood Control Structure along the Banks of Creeks along Kabatuhan Rd., Barangay 168, Caloocan City (Phase 3) is a DPWH-tracked public work in CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region. Reported contract value: ₱85,034,813.77. Status: Reported complete (DPWH). Contractor on record: DARCY & ANNA BUILDERS & TRADING. Figures trace to sumbong.

CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along the Banks of Creeks, along Carnacion Barangay 174, Caloocan City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Metro Manila 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱85,034,813.77

Progress

Reported complete (DPWH)

Start Date

April 24, 2023

Target End

March 18, 2024