Flood Control and Drainage18BG0030

CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT (PHASE 1) BARANGCUAG, CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT (PHASE 1) BARANGCUAG,

CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT (PHASE 1) BARANGCUAG, CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT (PHASE 1) BARANGCUAG, is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱28,462,581.57. Status: Reported complete (DPWH). Contractor on record: C R DOMINGO CONST AND POWER DEVELOPMENT INC FOR C R DOMINGO CONST INC. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Project (Phase I), Alicaocao, Cauayan City, Isabela
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-18-0015413

₱316,938.00 · FY2018

Released to Division of Davao Oriental (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, ROMAN EXPRESSWAY, PROVINCE OF BATAAN

Region III, Region III

2019₱131.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF QUIMALABASA NORTE FLOOD CONTROL STRUCTURE SECTION 5,

Isabela 4th DEO, Region II

2025₱106.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SANTIAGO CIRCUMFERENTIAL ROAD, ISABELA

Region II, Region II

2021₱104.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAUAYAN CITY BY-PASS ROAD, PACKAGE 1, ISABELA; STA. 000+000-STA. 001+085

Region II, Region II

2020₱103.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ), CORDON AND SANTIAGO, ISABELA

Region II, Region II

2020₱99.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES: VILLA GAMIAO, SAN ANTONIO, DARAMUANGAN SUR AND SALINUNGAN EAST ROADS CONNECTING TO MUNGGO PROCESSING AND PACKAGING CENTER

Region II, Region II

2021₱97.8M
Reported complete (DPWH)
View all 87 projects →

4. Implementation

Contract Amount

₱28,462,581.57

Progress

Reported complete (DPWH)

Start Date

April 19, 2018

Target End

November 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.