Flood Control and Drainage25LK0008

CONSTRUCTION OF REVETMENT ALONG ILANG CREEK, ILANG BRIDGE UPSTREAM, LEFT BANK, DAVAO CITY

CONSTRUCTION OF REVETMENT ALONG ILANG CREEK, ILANG BRIDGE UPSTREAM, LEFT BANK, DAVAO CITY is a DPWH-tracked public work in Davao City 3rd DEO, Region XI. Reported contract value: ₱95,058,352.21. Status: Past target date (DPWH On-Going). Contractor on record: DREIRICH BUILDERS. Figures trace to dpwh.

Davao City 3rd DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Boston River San Jose Section, Boston, Davao Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Davao City 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱95,058,352.21

Progress

Past target date (DPWH On-Going)

Start Date

April 8, 2025

Target End

January 15, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.