Construction of Flood Mitigation Structure24BG0043

Construction of Magat River Flood Control Project, Barangay Mallalatang Grande, Reina Mercedes, Isabela

Construction of Magat River Flood Control Project, Barangay Mallalatang Grande, Reina Mercedes, Isabela is a DPWH-tracked public work in REINA MERCEDES (ISABELA), ISABELA, Region II. Reported contract value: ₱96,398,901.52. Status: Reported complete (DPWH). Contractor on record: DANYSONS CONST AND DEVELOPMENT CORP FORMERLY: DANYSONS CONST. Figures trace to sumbong.

REINA MERCEDES (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Magat River Flood Control Structure, Brgy. Mallalatang Grande, Reina Mercedes, Isabela ( Phase III )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004352

₱1,853,487.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0009805

₱1,459,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0003846

₱276,213.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004354

₱173,574.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010584

₱135,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

138 projects · ₱4.1B total · 11 flags

4. Implementation

Contract Amount

₱96,398,901.52

Progress

Reported complete (DPWH)

Start Date

March 12, 2024

Target End

January 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.