Construction of Flood Mitigation Structure22KL0049

Construction of Flood Control Structure Igpit River (Package 1), Opol, Misamis Oriental

Construction of Flood Control Structure Igpit River (Package 1), Opol, Misamis Oriental is a DPWH-tracked public work in OPOL (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱53,541,974.18. Status: Reported complete (DPWH). Contractor on record: RITCHE-NATHALIE BUILDERS & GEN MERCHANDISE. Figures trace to sumbong.

OPOL (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures at Tagoloan River (Mohon Section), Misamis Oriental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002987

₱110,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002742

₱75,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003143

₱50,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003118

₱200,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005264

₱1,772,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005265

₱170,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0004831

₱47,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

30 projects · ₱2.1B total · 6 flags

4. Implementation

Contract Amount

₱53,541,974.18

Progress

Reported complete (DPWH)

Start Date

March 3, 2022

Target End

October 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.