Flood Control and Drainage25BI0041

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAM CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONT

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAM CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONT is a DPWH-tracked public work in Nueva Vizcaya DEO, Region II. Reported contract value: ₱143,302,870.55. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: DALCON CONST. Figures trace to dpwh.

Nueva Vizcaya DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Along Magat River, Sitio Kinacao, Brgy. Baretbet, Bagabag, Nueva Vizcaya
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Nueva Vizcaya DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱143,302,870.55

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 28, 2025

Target End

January 31, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.