GAA 2025 OO-225J00228

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DIPOLOG RIVER, BARANGAY DICAYAS, DIPOLOG CITY, ZAMBOANGA DEL NORTE

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DIPOLOG RIVER, BARANGAY DICAYAS, DIPOLOG CITY, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱173,321,200.00. Status: Past target date (DPWH On-Going). Contractor on record: BADSBRO CONST AND GEN MERCHANDISE. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱173,321,200.00

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

March 19, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.