Flood Control and Drainage18HL0010

CONST/REHAB OF FLOOD MITIGATION. . . CONSTRUCTION OF RIVER CONTROL ALONG BONAWON RIVER,SIATON,NEG OR

CONST/REHAB OF FLOOD MITIGATION. . . CONSTRUCTION OF RIVER CONTROL ALONG BONAWON RIVER,SIATON,NEG OR is a DPWH-tracked public work in Negros Oriental 3rd DEO, Negros Island Region. Reported contract value: ₱34,300,000.00. Status: Reported complete (DPWH). Contractor on record: JO BUILDERS 34470. Figures trace to dpwh.

Negros Oriental 3rd DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱34,300,000.00

Progress

Reported complete (DPWH)

Start Date

February 11, 2018

Target End

November 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.