Construction of Flood Mitigation Structure24BF0054

Construction of Mallig River Flood Control Project, Barangay San Juan Phase II, Sta. 1+100 - Sta. 1+900, Quirino, Isabela

Construction of Mallig River Flood Control Project, Barangay San Juan Phase II, Sta. 1+100 - Sta. 1+900, Quirino, Isabela is a DPWH-tracked public work in QUIRINO (ISABELA), ISABELA, Region II. Reported contract value: ₱96,470,259.43. Status: Reported complete (DPWH). Contractor on record: JWU CONST AND SUPPLY / ALGO CONST AND POWER DEVELOPMENT INC. Figures trace to sumbong.

QUIRINO (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mallig River Flood Control Project, Barangay San Juan, Quirino, Isabela Sta Sta 0 + 000 - Sta 0 + 388
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010520

₱1,488,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0001415

₱326,939.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0017379

₱202,867.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010581

₱137,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0001416

₱28,431.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,470,259.43

Progress

Reported complete (DPWH)

Start Date

April 15, 2024

Target End

March 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.