Flood Control and Drainage18IL0034

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS/ CONSTRUCTION OF GUINSANGAAN FLOOD CONTROL ALONG BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-DAANG MAHARLIKA (S00194LT) BONTOC, SOUTHERN LEYTE (CONSTRUCTION OF FLOOD MITIGATION STRUCT

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS/ CONSTRUCTION OF GUINSANGAAN FLOOD CONTROL ALONG BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-DAANG MAHARLIKA (S00194LT) BONTOC, SOUTHERN LEYTE (CONSTRUCTION OF FLOOD MITIGATION STRUCT is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱22,539,991.75. Status: Reported complete (DPWH). Contractor on record: UNIMASTERS CONGLOMERATION INC. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱23,000

    Probable match · score 0.89

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-E-18-0012182 · ₱40,000 · release to the district office, not itemized per project

    Possible match · score 0.76

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18IL0034 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-11-07 → 2025-09-30

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Southern Leyte

Based on the coordinates published with the DPWH record and NOAH file SouthernLeyte.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS/ CONSTRUCTION OF GUINSANGAAN FLOOD CONTROL ALONG BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-DAANG MAHARLIKA (S00194LT) BONTOC, SOUTHERN LEYTE (CONSTRUCTION OF FLOOD MITIGATION STRUCT

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Guinsangaan Flood Control along Bdry. So. Leyte-Maasin-Macrohon-Sogod- Daang Maharlika (S00194LT) Bontoc, Southern Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0012182

₱40,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

50 projects · ₱2.3B total · 0 flags

Other projects by this contractor

No sat.

ROAD WIDENING - PRIMARY ROADS - PALO - CARIGARA - ORMOC ROAD - KO975+061 - KO975+788, KO975+832.20 - KO980+372, KO982+186 - KO983+255, KO940+454 - KO940+895, LEYTE 2ND LD

Region VIII, Region VIII

2018₱165.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASSES ROAD, INCLUDING ROW NRJ DAANG MAHARLIKA, TAGUIBO-MASAO PORT, (CABCABON-BANZA SECTION), BUTUAN CITY, AGUSAN DEL NORTE 1ST LD., BUTUAN CITY, AGUSAN DEL NORTE 1ST LD.

Region XIII, Region XIII

2016₱140.3M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD. - K0953+466 - K0954+288, K0954+299 - K0955+000, K0955+000 - K0955+344, K0955+357 - K0956+233, CARIGARA, LEYTE 2ND LD

Region VIII, Region VIII

2020₱122.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SAN FRANCISCO (NRJ HUBANG - STA. ANA - SAN ISIDRO) BYPASS ROAD (DAANG MAHARLIKA ALTERNATE ROUTE), INCLUDING ROW AND BRIDGE, SAN FRANCISCO, AGUSAN DEL SUR

Region XIII, Region XIII

2018₱119.8M
Reported complete (DPWH)
No sat.

IMPROVEMENT/WIDENING OF NATIONAL ROADS, DAANG MAHARLIKA (SURIGAO-AGUSAN SECT.), K1197+550-K1199+289.40, K1202+000-K1202+812.46, K1202+911.75-K1203+238, AGUSAN DEL NORTE

Region XIII, Region XIII

2017₱102.3M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF DIKE WITH CONCRETE REVETMENT ALONG PANDANON - MAGALLANES ROAD, AGUSAN DEL NORTE

Agusan del Norte DEO, Region XIII

2020₱96.5M
Reported complete (DPWH)
View all 50 projects →

4. Implementation

Contract Amount

₱22,539,991.75

Progress

Reported complete (DPWH)

Start Date

February 22, 2018

Target End

September 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)Southern LeyteBontocCawayanan
Storms whose wind field reached it
Penha 2026Koto 2025Kalmaegi 2025
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →