Roads20MG0152

CONSTRUCTION OF CONCRETE ROAD-JCT. (BEN SIDON)-BACDULONG ROAD LEADING TO LAKE SEBU (LAKE SEBU CIRCUMFERENTIAL ROAD), BRGY. BACDULONG, LAKE SEBU, SOUTH COTABATO

CONSTRUCTION OF CONCRETE ROAD-JCT. (BEN SIDON)-BACDULONG ROAD LEADING TO LAKE SEBU (LAKE SEBU CIRCUMFERENTIAL ROAD), BRGY. BACDULONG, LAKE SEBU, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱35,933,624.46. Status: Reported complete (DPWH). Contractor on record: BETTER WORK CONST. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Banga River,Brgy. Malaya, Banga, South Cotabato
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

South Cotabato 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱35,933,624.46

Progress

Reported complete (DPWH)

Start Date

January 8, 2021

Target End

July 1, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.