Construction of Flood Mitigation Structure22AA0151

Construction of Flood Mitigation Structure along Vintar River (Bislak River), Brgy. Alsem, Sitio Namnama, Vintar, Ilocos Norte

Construction of Flood Mitigation Structure along Vintar River (Bislak River), Brgy. Alsem, Sitio Namnama, Vintar, Ilocos Norte is a DPWH-tracked public work in VINTAR (ILOCOS NORTE), ILOCOS NORTE, Region I. Reported contract value: ₱43,559,717.83. Status: Reported complete (DPWH). Contractor on record: JCA CONST AND CONST SUPPLY. Figures trace to sumbong.

VINTAR (ILOCOS NORTE), ILOCOS NORTE, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱44,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Vintar River (Bislak River), Brgy. Alsem, Sitio Namnama, Vintar, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002978

₱1,132,084,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003109

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0011001

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002617

₱25,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

133 projects · ₱2.4B total · 6 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, GUMACA-PITOGO-MULANAY-SN. NARCISO RD., K0202+745 - K0206+531, GUMACA,

Quezon 4th DEO, Region IV-A

2025₱93.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS, QUIRINO HIGHWAY, K0253+000 - K0254+209, GUINAYANGAN, QUEZON

Quezon 4th DEO, Region IV-A

2025₱93.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MANILA NORTH ROAD - K0578+645 - K0578+700, PAGUDPUD, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2021₱92.6M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MALING RIVER, ATIMONAN, QU

Quezon 4th DEO, Region IV-A

2025₱90.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SEAWALL ALONG BURGOS BAY, BRGY. BOBON SECTION AND BRGY. PAAYAS SECTION, MUNICIPALITY OF BURGOS, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2022₱86.8M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, BRGY. DIPILAT, MUNICIPALITY OF VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2022₱85.9M
Reported complete (DPWH)
View all 133 projects →

4. Implementation

Contract Amount

₱43,559,717.83

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

October 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.