Roads23HG0049

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM; ASSET PRESERVATION PROGRAM; REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS: N. BACALSO AVE (CEBU SOUTH RD) - K0081+621.00 - K0081+670

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM; ASSET PRESERVATION PROGRAM; REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS: N. BACALSO AVE (CEBU SOUTH RD) - K0081+621.00 - K0081+670 is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱96,040,000.00. Status: Reported complete (DPWH). Contractor on record: ZLREJ TRADING AND CONST CORP. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Tabunok, Talisay City, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

119 projects · ₱8.5B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CEBU SOUTH COASTAL RD - (S00015CB) CHAINAGE 510 - CHAINAGE 1019

Region VII, Region VII

2025₱221.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CEBU SOUTH COASTAL RD - CHAINAGE 0 - CHAINAGE 510

Region VII, Region VII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURES AT BRGY. GUINTABOAN, UBAY, BOHOL

Region VII, Region VII

2024₱192.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, CANSAGA BAY BR. (B00613CB) ALONG CANSAGA BAY BRIDGE, CEBU

Region VII, Region VII

2022₱173.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, VIADUCT BR. (B00081CB) ALONG CEBU SOUTH COASTAL RD

Region VII, Region VII

2024₱173.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MARCELO FERNAN BR. (B00619CB) ALONG MARCELO B. FERNAN BR. & APPROACHES

Region VII, Region VII

2024₱173.7M
Reported complete (DPWH)
View all 119 projects →

4. Implementation

Contract Amount

₱96,040,000.00

Progress

Reported complete (DPWH)

Start Date

May 18, 2023

Target End

March 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.