Construction of Flood Mitigation Structure23N00184

Construction of Flood Control Structures along Lake Mainit - Tubay River (Kalinawan-Karak-an Section), Package 3, Tubay, Agusan del Norte

Construction of Flood Control Structures along Lake Mainit - Tubay River (Kalinawan-Karak-an Section), Package 3, Tubay, Agusan del Norte is a DPWH-tracked public work in TUBAY (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII. Reported contract value: ₱159,223,478.10. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to sumbong.

TUBAY (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mamkas Flood Control Project, Brgy. Mamkas, Kitcharao, Agusan del Norte (Package 2)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Agusan del Norte District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

21 projects · ₱2.3B total · 0 flags

Other projects by this contractor

Rehabilitation of Bank Protection Structure along Taguibo River Protecting Taguibo Dam Water-Filtration Facilities, Package 2, Barangay Anticala, Butuan City, Agusan del Norte

BUTUAN CITY (CAPITAL) (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII

2024₱193.0M
Reported complete (DPWH)

Construction of Flood Control Structure along Iponan River, Package 9, Cagayan de Oro City

CAGAYAN DE ORO CITY (CAPITAL) (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X

2024₱146.1M
Reported complete (DPWH)

Rehabilitation of Dike along Mandakpan-Bonbon Channel, Downstream Section, Butuan City, Agusan Del Norte

BUTUAN CITY (CAPITAL) (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII

2023₱144.7M
Reported complete (DPWH)

Construction of Drainage System along Butuan City-Cagayan de Oro-Iligan Road, Silongan St. to Jct Montilla Blvd (Both Sides) including sidewalk, curb and gutter, Butuan City, Agusan Del Norte

BUTUAN CITY (CAPITAL) (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII

2023₱144.7M
Reported complete (DPWH)

Construction (Completion) of Main Drainage Canal Along Montilla JCT Montilla Boulevard - Salvador Calo Street to Main LADP Main Drainage Canal Butuan City, Agusan del Norte

BUTUAN CITY (CAPITAL) (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII

2023₱144.7M
Reported complete (DPWH)

Construction of Dike with Concrete Revetment along Bangonay River, Downstream Section along Abutment B of the Bridge, Jabonga, Agusan del Norte

JABONGA (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII

2022₱139.9M
Reported complete (DPWH)
View all 21 projects →

4. Implementation

Contract Amount

₱159,223,478.10

Progress

Reported complete (DPWH)

Start Date

July 20, 2023

Target End

May 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.