Flood Control and Drainage17LC0020

TAGUM-LIBUGANON RIVER FLOOD CONTROL STA. 5 + 600 - STA. 6 + 376, STA. 0 + 040- STA. 0+160, STA. 8 +739-STA. 8 + 879.20 INCLUDING RROW, DAVAO DEL NORTE

TAGUM-LIBUGANON RIVER FLOOD CONTROL STA. 5 + 600 - STA. 6 + 376, STA. 0 + 040- STA. 0+160, STA. 8 +739-STA. 8 + 879.20 INCLUDING RROW, DAVAO DEL NORTE is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱36,023,160.00. Status: Reported complete (DPWH). Contractor on record: DAVAO CONCRETE PRODUCTS CONST AND TRADING CORP FORMERLY: DAVAO CONCRETE PRODUCTS. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱38,442,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Tagum Libuganon River Flood Control, Sta. 5+600 - Sta. 6+376, Sta. 0+040 - Sta. 0+160, Sta. 8+739 - Sta. 8+879.20 Including ROW, Davao del Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0025737

₱6,325,000.00 · FY2017

Released to Iwahig Prison an Penal Farm (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

47 projects · ₱816.5M total · 0 flags

4. Implementation

Contract Amount

₱36,023,160.00

Progress

Reported complete (DPWH)

Start Date

March 3, 2017

Target End

September 6, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.