Flood Control and Drainage19MH0085

CONSTRUCTION OF FLOOD CONTROL (ALA RIVER BASIN) ESPERANZA, SULTAN KUDARAT

CONSTRUCTION OF FLOOD CONTROL (ALA RIVER BASIN) ESPERANZA, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱46,424,524.58. Status: Reported complete (DPWH). Contractor on record: LLABAN CONST & SUPPLY FORMERLY: LLABAN CON. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0021904

₱9,500,000.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱46,424,524.58

Progress

Reported complete (DPWH)

Start Date

July 4, 2019

Target End

February 3, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.