Construction of Flood Mitigation Structure22K00225

Construction of Flood Control Structure along Naawan River Downstream of Naawan Bridge (Left Side), Package 2, Naawan, Misamis Oriental

Construction of Flood Control Structure along Naawan River Downstream of Naawan Bridge (Left Side), Package 2, Naawan, Misamis Oriental is a DPWH-tracked public work in NAAWAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱137,503,763.40. Status: Reported complete (DPWH). Contractor on record: TRIPARCO DEVELOPMENT CORP. Figures trace to sumbong.

NAAWAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures at Tagoloan River (Natumolan Section), Package 7, Misamis Oriental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002987

₱110,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002742

₱75,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003143

₱50,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003118

₱200,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005264

₱1,772,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005265

₱170,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0004831

₱47,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

357 projects · ₱29.2B total · 4 flags

Other projects by this contractor

View all 357 projects →

4. Implementation

Contract Amount

₱137,503,763.40

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

July 8, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.