Published flags in Nueva Vizcaya
57 published flags on records linked to Nueva Vizcaya and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C7 · High Concurrent Workload for One ContractorEgb Const Corp Formerly: Egb ConstContractor (applies to all its work) · contractor Egb Const Corp Formerly: Egb Const
- C7 · High Concurrent Workload for One ContractorNorthern BuildersContractor (applies to all its work) · contractor Northern Builders
- C7 · High Concurrent Workload for One ContractorDalcon ConstContractor (applies to all its work) · contractor Dalcon Const
- C7 · High Concurrent Workload for One ContractorRoad Edge Trading & Development ServicesContractor (applies to all its work) · contractor Road Edge Trading & Development Services
- C7 · High Concurrent Workload for One ContractorRosbill Const and SupplyContractor (applies to all its work) · contractor Rosbill Const and Supply
- C7 · High Concurrent Workload for One ContractorAnore ConstContractor (applies to all its work) · contractor Anore Const
- C5 · Pattern Consistent with Contract SplittingRehabilitation of Flood Control Along Sta. Cruz River, Barat Section, Bambang, Nueva VizcayaDPWH project · contractor J E L Const & Supply
- C5 · Pattern Consistent with Contract SplittingRehabilitation of Flood Control Along Cupas River, San Leonardo Section, Bambang, Nueva VizcayaDPWH project · contractor J E L Const & Supply
- C5 · Pattern Consistent with Contract SplittingRehabilitation of Flood Control Along Sta. Cruz River, Aliaga Section, Bambang, Nueva VizcayaDPWH project · contractor J E L Const & Supply
- C7 · High Concurrent Workload for One ContractorSt Timothy Const CorpContractor (applies to all its work) · contractor St Timothy Const Corp
- C7 · High Concurrent Workload for One ContractorV B Manubay ConstContractor (applies to all its work) · contractor V B Manubay Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structures at Comon Section, Aritao, Nueva VizcayaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const
- C1 · Contractor Concentration (Flood Control)Rosbill Const and SupplyContractor (applies to all its work) · contractor Rosbill Const and Supply
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structures at Comon-Latar Section, Aritao, Nueva VizcayaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / Kevin Paul Const
- C1 · Contractor Concentration (Flood Control)W J P Const and SupplyContractor (applies to all its work) · contractor W J P Const and Supply
- C1 · Contractor Concentration (Flood Control)Brg ConstContractor (applies to all its work) · contractor Brg Const
- C1 · Contractor Concentration (Flood Control)Jejor'S Const CorpContractor (applies to all its work) · contractor Jejor'S Const Corp
- C2 · Awards Very Close to the Budget CeilingConstruction of Bakir Flood Control Structure Along Lamut River, Barangay Bakir, Bagabag, Nueva VizcayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C4 · Schedule / Date InconsistenciesRehabilitation of Flood Control Structure Along Magat River, Sto. Domingo Section, Package 2, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds- Package 2) Along Magat River, Magapuy Section, Bayombong, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structure Along Cupaz River, San Leonardo Section, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Magat River, Barangay Magsaysay, Bayombong, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structure Along Magat River, Tuao South Section, Bagabag, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structure Along Magat River, Baretbet Section, Bagabag, Nueva VizcayaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control and Drainage Structures (Fcds- Package 5) Along Magat River, Bagahabag Section, Solano, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingRehabilitation of Flood Control Structure Along Santa Cruz River, Barangay Salinas, Bambang, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds) Along Magat River, Kinacao Section, Bagabag, Nueva VizcayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structure Along Magat River, Tuao North Section, Bagabag, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Nalubbunan Flood Control Structure, Angadanan River, Nalubbunan, Quezon, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingRehabilitation of Flood Control Structure Along Magat River, Sto. Vista Alegra Section, Package 1, Bayombong, Nueva VizcayaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control and Drainage Structures (Fcds- Package 6) Along Magat River, Santa Lucia Section, Bagabag, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control and Drainage Structures (Fcds- Package 2) Along Magat River, Magapuy Section, Bayombong, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control and Drainage Structures (Fcds- Package 7) Along Magat River, Magapuy Section, Bayombong, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds- Package 7) Along Magat River, Magapuy Section, Bayombong, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C4 · Schedule / Date InconsistenciesConstruction of Manamtam Floos Control Along Matuno River (Section 2), Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds- Package 8) Along Magat River, Baretbet Section, Bagabag, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingRehabilitation of Flood Control Structure Along Magat River (Phase 2), Barangay Sta. Rosa, Bayombong, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Busilac - Magsaysay Flood Control (Busilac Section) at Barangay Busilac, Bayombong, Nueva VizcayaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Buenavista - Busilac Flood Control Structure Along Magat River, Bayombong, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds- Package 5) Along Magat River, Bagahabag Section, Solano, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingRehabilitation of Flood Control Structure Along Magat River, (Phase 1) Barangay Busilac, Bayombong, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds) Along Sta. Fe River, Almaguer North Section, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control and Drainage Structure Along Matuno River, Manamtam Section, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structure Along Matuno River, Barat Section, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Tuao North-Tuao South Flood Control Structure Along Magat River, Sitio Dumayop, Tuao North-Tuao South, Bagabag, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Santa Fe River, Barangay Aliaga, Bambang, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control and Drainage Structure Along Matuno River, Barat Section, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structure Along Magat River, Magapuy Section, Bayombong, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds- Package 3) Along Magat River, Baretbet Section, Bagabag, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structure Along Matuno River, Manamtam Section, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Sta. Lucia Flood Control Structure Along Lamut River, Barangay Sta. Lucia, Bagabag, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingRehabilitation of Flood Control Structure Along Magat River, Sto. Domingo Section, Package 2, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control and Drainage Structures (Fcds- Package 6) Along Magat River, Santa Lucia Section, Bagabag, Nueva ViscayaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Manamtam Floos Control Along Matuno River (Section 2), Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along Santa Fe River, Barangay Aliaga, Bambang, Nueva VizcayaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Buenavista - Busilac Flood Control Structure Along Magat River, Bayombong, Nueva VizcayaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control and Drainage Structure Along Cupaz River, San Leonardo Section, Bambang, Nueva VizcayaDPWH project · contractor Dalcon Const
Named parties may reply or request a correction. See the methodology.