Flood Control and Drainage18A00104

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD CONTROL ALONG ABRA RIVER, BANTAY SECTION, PHASE II, BANTAY, ILOCOS SUR

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD CONTROL ALONG ABRA RIVER, BANTAY SECTION, PHASE II, BANTAY, ILOCOS SUR is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱98,275,842.33. Status: Reported complete (DPWH). Contractor on record: A P B CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

202 projects · ₱7.5B total · 1 flags

4. Implementation

Contract Amount

₱98,275,842.33

Progress

Reported complete (DPWH)

Start Date

May 21, 2018

Target End

March 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.