Construction of Flood Mitigation Structure21FH0065

Construction of Seawall, Municipality of Caramoran, Catanduanes

Construction of Seawall, Municipality of Caramoran, Catanduanes is a DPWH-tracked public work in CATANDUANES, Region V. Reported contract value: ₱29,397,518.79. Status: Reported complete (DPWH). Contractor on record: JASMIN CONST. Figures trace to sumbong.

CATANDUANES, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱14,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Seawall), Barangay Baybay, Caramoran, Catanduanes
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱404,461,000.00 · FY2021

Released to Cavite 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007545

₱71,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013873

₱45,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013886

₱81,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007593

₱9,792,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011481

₱30,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014195

₱80,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱29,397,518.79

Progress

Reported complete (DPWH)

Start Date

September 6, 2022

Target End

February 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.