Construction of Flood Mitigation Structure24IF0018

Construction of Donghol Flood Control Structure, Ormoc City, Leyte

Construction of Donghol Flood Control Structure, Ormoc City, Leyte is a DPWH-tracked public work in ORMOC CITY (LEYTE), LEYTE, Region VIII. Reported contract value: ₱96,399,999.99. Status: Reported complete (DPWH). Contractor on record: JM COLLERA KONSTRACT. Figures trace to sumbong.

ORMOC CITY (LEYTE), LEYTE, Region VIII
Region: Region VIII

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.93

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROXI-24-0013247 · ₱1,590,000 · release to the district office, not itemized per project

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱96,400,000 · JM COLLERA KONSTRACT

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-08-04 → 2025-04-15

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Leyte

Based on the coordinates published with the DPWH record and NOAH file Leyte.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Construction of Donghol Flood Control Structure, Ormoc City, Leyte

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Hipusngo Flood Control Structure, Barangay Hipusngo, Baybay City, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-24-0013247

₱1,590,000.00 · FY2024

Released to Division of Mati City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008533

₱1,669,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008534

₱154,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0005347

₱1,241,883.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0017756

₱700,547.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,399,999.99

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

December 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)LeyteOrmoc CityDonghol
Storms whose wind field reached it
Nokaen 2026Koto 2025Kalmaegi 2025Bualoi 2025Prapiroon 2024
Hazard exposure
Flood (100-yr rain)LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.