Flood Control and Drainage25GJ0015

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN ILOILO CITY WATERWAYS, SECTION 3

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN ILOILO CITY WATERWAYS, SECTION 3 is a DPWH-tracked public work in Iloilo City DEO, Region VI. Reported contract value: ₱102,798,574.13. Status: Past target date (DPWH On-Going). Contractor on record: F GURREA CONST INC. Figures trace to dpwh.

Iloilo City DEO, Region VI
Region: Region VI

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱40,000

    Probable match · score 0.88

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-D-25-0016891 · ₱1,680,345 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱102,798,574 · F GURREA CONST INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    21% reported · imagery 2022-11-29 → 2024-12-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Iloilo

Based on the coordinates published with the DPWH record and NOAH file Iloilo.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN ILOILO CITY WATERWAYS, SECTION 3

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures within Iloilo City Waterways and Coastal Protection (Section 11)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-25-0016891

₱1,680,345.00 · FY2025

Released to Regional Office - VIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱102,798,574.13

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

January 8, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VI (Western Visayas)City of IloiloDivinagracia
Storms whose wind field reached it
Penha 2026Koto 2025Kalmaegi 2025Bualoi 2025
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.