GAA 2023 Augmentation23H00122

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LUYANG RIVER, CARMEN, CEBU

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LUYANG RIVER, CARMEN, CEBU is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱79,567,499.99. Status: Past target date (DPWH On-Going). Contractor on record: GONZALODO ENT. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

297 projects · ₱8.5B total · 1 flags

4. Implementation

Contract Amount

₱79,567,499.99

Progress

Past target date (DPWH On-Going)

Start Date

December 31, 2024

Target End

December 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.