Construction of Flood Mitigation Structure21BG0151

Construction of Flood Control Structure along Ganano River Bank, Barangay San Antonio, Alicia, Isabela

Construction of Flood Control Structure along Ganano River Bank, Barangay San Antonio, Alicia, Isabela is a DPWH-tracked public work in ISABELA, Region II. Reported contract value: ₱96,427,479.98. Status: Reported complete (DPWH). Contractor on record: A DE GUIA CONST AND DEVELOPMENT CORP FORMERLY: A DE GUIA CONST. Figures trace to sumbong.

ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱10,765,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure , Quimalabasa Section, San Agustin, Isabela
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014116

₱98,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010266

₱50,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005370

₱10,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013822

₱209,045,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-21-0002244

₱573,315.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-21-0002245

₱49,609.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007536

₱2,000,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,427,479.98

Progress

Reported complete (DPWH)

Start Date

November 23, 2021

Target End

October 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.