ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT. AYAGA (ABULUG)-BALLESTEROS-APARRI RD - K0674+241-K0677+366, K0681+000-K0682+345
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT. AYAGA (ABULUG)-BALLESTEROS-APARRI RD - K0674+241-K0677+366, K0681+000-K0682+345 is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱71,289,305.84. Status: Reported complete (DPWH). Contractor on record: SKYLINE CONST EQUIPMENT AND DEVELOPMENT CORP FORMERLY: EDDIE G GUILLEN BUILDERS INC. Figures trace to dpwh.