Construction of Flood Mitigation Structure24CD0169

Construction of Flood Control Structure, Barangay Francisco Homes Guijo - Barangay Yakal, San Jose del Monte, Bulacan

Construction of Flood Control Structure, Barangay Francisco Homes Guijo - Barangay Yakal, San Jose del Monte, Bulacan is a DPWH-tracked public work in CITY OF SAN JOSE DEL MONTE (BULACAN), BULACAN, Region III. Reported contract value: ₱48,257,590.02. Status: Reported complete (DPWH). Contractor on record: TRIPLE 8 CONST & SUPPLY INC FORMERLY TRIPLE 8 CONST & SUPPLY. Figures trace to sumbong.

CITY OF SAN JOSE DEL MONTE (BULACAN), BULACAN, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Francisco Homes Guijo - Barangay Yakal, San Jose del Monte, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007287

₱1,460,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000163

₱1,078,312.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0006660

₱9,979,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0016339

₱108,080.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007288

₱135,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROXI-24-0015351

₱553,291.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,257,590.02

Progress

Reported complete (DPWH)

Start Date

April 30, 2024

Target End

February 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.