Rehabilitation / Major Repair of Flood Control Structure24GA0135

Rehabilitation of Seawall, Brgy. Tambak, New Washington, Aklan

Rehabilitation of Seawall, Brgy. Tambak, New Washington, Aklan is a DPWH-tracked public work in NEW WASHINGTON (AKLAN), AKLAN, Region VI. Reported contract value: ₱29,399,995.16. Status: Reported complete (DPWH). Contractor on record: GREENLAND BUILDERS. Figures trace to sumbong.

NEW WASHINGTON (AKLAN), AKLAN, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aklan River, Kalibo, Aklan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0005147

₱40,000.00 · FY2024

Released to Mauaque High School (resettlement school) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0009975

₱1,529,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0009977

₱141,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

Probable match · 89%

23GA0176 - Rehabilitation of Aklan West Road

₱28,370,999.98 · GREENLAND BUILDERS

4. Implementation

Contract Amount

₱29,399,995.16

Progress

Reported complete (DPWH)

Start Date

April 22, 2024

Target End

November 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.