Construction of Flood Mitigation Structure23CA0027

Construction of Flood Control Structure along Colo River, Sacrifice Valley Section (Phase II-AA), Hermosa, Bataan

Construction of Flood Control Structure along Colo River, Sacrifice Valley Section (Phase II-AA), Hermosa, Bataan is a DPWH-tracked public work in HERMOSA (BATAAN), BATAAN, Region III. Reported contract value: ₱67,549,999.36. Status: Reported complete (DPWH). Contractor on record: AVE-MIRA CONST AND TRADING / ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS & SUPPLY. Figures trace to sumbong.

HERMOSA (BATAAN), BATAAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tuyo River, Abucay Section (Phase II-AA), Abucay, Bataan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bataan 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱67,549,999.36

Progress

Reported complete (DPWH)

Start Date

March 30, 2023

Target End

November 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.