Flood Control and Drainage24DF0204

CONVERGENCE & SPECIAL SUPPORT PROG BASIC INFRA PROG (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BLDGS/ FACILITIESCONST OF SLOPE PROTECTION IN SANTIAGO INTEGRATED SENIOR HIGH SCHOOL, BRGY SANTIAGO, GEN TRIAS CITY, CAVITE

CONVERGENCE & SPECIAL SUPPORT PROG BASIC INFRA PROG (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BLDGS/ FACILITIESCONST OF SLOPE PROTECTION IN SANTIAGO INTEGRATED SENIOR HIGH SCHOOL, BRGY SANTIAGO, GEN TRIAS CITY, CAVITE is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱19,592,795.76. Status: Reported complete (DPWH). Contractor on record: R V RIETA TRADING. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Tibig, Silang, Cavite
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0015638

₱1,322,839.00 · FY2024

Released to Cavite 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,592,795.76

Progress

Reported complete (DPWH)

Start Date

April 17, 2024

Target End

September 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.