Roads23F00154

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-SAN FERNANDO-SAN JACINTO-MONREAL ROAD, PACKAGE 2, MASBATE, SAN JACINTO, MASBATE (1ST LEGISLATIVE DISTRICT)

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-SAN FERNANDO-SAN JACINTO-MONREAL ROAD, PACKAGE 2, MASBATE, SAN JACINTO, MASBATE (1ST LEGISLATIVE DISTRICT) is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱33,579,728.03. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ALGIMAR CONST CORP. Figures trace to dpwh.

Region V, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23F00154 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-05-25 → 2025-10-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-SAN FERNANDO-SAN JACINTO-MONREAL ROAD, PACKAGE 2, MASBATE, SAN JACINTO, MASBATE (1ST LEGISLATIVE DISTRICT)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

68 projects · ₱2.9B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0265+346-K0266+470, K0267+053-K0267+112, STA. ELENA, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2024₱136.8M
Past target date (DPWH On-Going)
No sat.

MFO1 - OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE-SECONDARY ROADS; MASBATE-CATAINGAN-PLACER ROAD, K0025+420 TO K0036+850 WITH EXCEPTIONS, CATAINGAN AND PLACER, MASBATE PROVINCE

Region V, Region V

2017₱132.6M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (GRAVEL TO CONC.) JCT. TAGBAK-LUBANG-LOOC RD.-BINACAS RD., KO009+625 (STA. 009+625.00)-KO012+273 (STA. 012+265.00), KO012+664 (STA. 012+664.00)-KO012+876 (STA. 012+880.00), KO012+976 (STA. 013+051.00)-KO014+172.80 (STA. 014+265.00), KO014+2

Region IV-B, Region IV-B

2016₱118.1M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-TAGKAWAYAN-LABO DIVERSION ROAD, LABO SECTION, CAMARINES NORTE, LABO, CAMARINES NORTE 1ST LEGISLATIVE DISTRICT

Region V, Region V

2023₱110.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF TALISAY COASTAL ROAD, MASBATE, SAN FERNANDO, MASBATE (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2023₱99.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF SAN FERNANDO - SAN JACINTO - MONREAL ROAD, MASBATE.

Masbate 1st DEO, Region V

2023₱99.0M
Reported complete (DPWH)
View all 68 projects →

4. Implementation

Contract Amount

₱33,579,728.03

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 19, 2023

Target End

September 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)MasbateSan JacintoBagacay
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.