Flood Control and Drainage24AI0140

CONSTRUCTION OF DRAINAGE SYSTEM, ARELLANO-ZAMORA STREET, BARANGAY POBLACION, BINALONAN, PANGASINAN

CONSTRUCTION OF DRAINAGE SYSTEM, ARELLANO-ZAMORA STREET, BARANGAY POBLACION, BINALONAN, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱14,811,038.43. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JOJEAN CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱14,479,173 · JOJEAN CONSTRUCTION AND DEVELOPMENT

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2024-02-18 → 2025-11-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Low flood hazard · Pangasinan

Based on the coordinates published with the DPWH record and NOAH file Pangasinan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF DRAINAGE SYSTEM, ARELLANO-ZAMORA STREET, BARANGAY POBLACION, BINALONAN, PANGASINAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aloragat River, Barangay Bugayong - Vacante, Binalonan, Pangasinan ( Package 4 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Pangasinan 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Drainage System, Arellano-Burgos-Z

₱14,479,172.68 · JOJEAN CONSTRUCTION AND DEVELOPMENT

4. Implementation

Contract Amount

₱14,811,038.43

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 12, 2024

Target End

October 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region I (Ilocos Region)PangasinanBinalonanPoblacion
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Kajiki 2025Co-May 2025
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.