Construction of Flood Mitigation Structure22K00195

Construction of Flood Mitigation Structure along Tagoloan River, Package 2, Misamis Oriental

Construction of Flood Mitigation Structure along Tagoloan River, Package 2, Misamis Oriental is a DPWH-tracked public work in TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱65,153,251.90. Status: Reported complete (DPWH). Contractor on record: TRIPARCO DEVELOPMENT CORP. Figures trace to sumbong.

TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures at Tagoloan River (Natumolan Section), Package 7, Misamis Oriental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002987

₱110,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002742

₱75,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003143

₱50,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003118

₱200,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005264

₱1,772,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005265

₱170,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0004831

₱47,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

357 projects · ₱29.2B total · 4 flags

Other projects by this contractor

View all 357 projects →

4. Implementation

Contract Amount

₱65,153,251.90

Progress

Reported complete (DPWH)

Start Date

May 23, 2022

Target End

July 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.