Construction of Flood Mitigation Structure23HH0126

Construction of Flood Mitigation Structure, Barangay Basak San Nicolas, Cebu City, Cebu

Construction of Flood Mitigation Structure, Barangay Basak San Nicolas, Cebu City, Cebu is a DPWH-tracked public work in CEBU CITY (CAPITAL) (CEBU), CEBU, Region VII. Reported contract value: ₱11,834,060.05. Status: Reported complete (DPWH). Contractor on record: YES CONST. Figures trace to sumbong.

CEBU CITY (CAPITAL) (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Basak San Nicolas, Cebu City, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu City District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

56 projects · ₱323.3M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ADLAYAN RIVERBANK (DOWNSTREAM), BRGY. HUBANG, SAN FRANCISCO, AGUSAN DEL SUR

Agusan del Sur 2nd DEO, Region XIII

2025₱45.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BANK PROTECTION ALONG GIBONG RIVER (MAYGATASAN SECTION) DOWNSTREAM, BRGY. MAYGATASAN, BAYUGAN CITY, AGUSAN DEL SUR, BAYUGAN CITY, AGUSAN DEL SUR

Agusan del Sur 1st DEO, Region XIII

2025₱29.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM, DESTINATION AT BRGY. HIMENSULAN - BRGY. SANTIAGO LEADING TO SANTIAGO PUBLIC BEACH RESORT, BRGY. HIMENSULAN, SAN FRANCISCO, CEBU

Cebu 5th DEO, Region VII

2018₱18.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0029+1860 K0031+351, SAN FERNANDO, C

Cebu 1st DEO, Region VII

2024₱16.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0009 + 155 - K0009 + 467, TALISAY CI

Cebu 1st DEO, Region VII

2025₱12.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0031+220 - K0031+351, SAN FERNANDO, CEBU

Cebu 1st DEO, Region VII

2024₱10.3M
Reported complete (DPWH)
View all 56 projects →

4. Implementation

Contract Amount

₱11,834,060.05

Progress

Reported complete (DPWH)

Start Date

November 15, 2023

Target End

May 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.