Construction of Flood Mitigation Structure24OF0021

Construction of Flood Control Structure at Barangay San Bartolome, Quezon City (Phase II)

Construction of Flood Control Structure at Barangay San Bartolome, Quezon City (Phase II) is a DPWH-tracked public work in QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region. Reported contract value: ₱48,508,937.83. Status: Reported complete (DPWH). Contractor on record: AVE-MIRA CONST AND TRADING. Figures trace to sumbong.

QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay San Bartolome, Quezon City ( Phase II )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008750

₱1,815,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0003156

₱1,401,164.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000559

₱1,853,574.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008765

₱168,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0003157

₱123,131.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000560

₱173,180.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

99 projects · ₱1.5B total · 0 flags

4. Implementation

Contract Amount

₱48,508,937.83

Progress

Reported complete (DPWH)

Start Date

February 6, 2024

Target End

December 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.