Rehabilitation / Major Repair of Flood Control Structure22BI0046

Rehabilitation of Flood Control and Drainage Structures along Magat River, Vista Alegre Section (Phase 5), Sta. 0 + 363.85 - Sta. 0 + 413.85, Sta. 0 + 593.85 - Sta. 0 + 893.85, Bayombong, Nueva Vizcaya

Rehabilitation of Flood Control and Drainage Structures along Magat River, Vista Alegre Section (Phase 5), Sta. 0 + 363.85 - Sta. 0 + 413.85, Sta. 0 + 593.85 - Sta. 0 + 893.85, Bayombong, Nueva Vizcaya is a DPWH-tracked public work in BAYOMBONG (CAPITAL) (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II. Reported contract value: ₱28,950,000.00. Status: Reported complete (DPWH). Contractor on record: G M PAJARILLAGA CONST & SUPPLY. Figures trace to sumbong.

BAYOMBONG (CAPITAL) (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control and Drainage Structures along Magat River, Vista Alegre Section (Phase 5), Sta. 0 + 363.85 - Sta. 0 + 413.85, Sta. 0 + 593.85 - Sta. 0 + 893.85, Bayombong, Nueva Vizcaya
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0011002

₱75,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002786

₱33,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002432

₱21,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002996

₱409,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0002544

₱310,863.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0002545

₱27,137.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0008154

₱5,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱28.9M total · 0 flags

4. Implementation

Contract Amount

₱28,950,000.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2022

Target End

November 15, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.