Construction of Flood Mitigation Structure23HA0018

Construction of Flood Mitigation Structure and Drainage System of Cantomimbo Flood Control, Balilihan, Bohol

Construction of Flood Mitigation Structure and Drainage System of Cantomimbo Flood Control, Balilihan, Bohol is a DPWH-tracked public work in BALILIHAN (BOHOL), BOHOL, Region VII. Reported contract value: ₱4,885,000.00. Status: Reported complete (DPWH). Contractor on record: HUSAIN CONST AND SUPPLY CO. Figures trace to sumbong.

BALILIHAN (BOHOL), BOHOL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure and Drainage System of Cantomimbo Flood Control, Balilihan, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bohol 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

43 projects · ₱272.5M total · 0 flags

4. Implementation

Contract Amount

₱4,885,000.00

Progress

Reported complete (DPWH)

Start Date

February 16, 2023

Target End

April 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.