Flood Control and Drainage18CD0017

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG STA. MARIA RIVER (BAGBAGUIN SECTION), STA. MARIA, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG STA. MARIA RIVER (BAGBAGUIN SECTION), STA. MARIA, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱79,854,170.41. Status: Reported complete (DPWH). Contractor on record: C T LEONCIO CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱50,000

    Probable match · score 0.92

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROIX-18-0034392 · ₱139,000 · release to the district office, not itemized per project

    Possible match · score 0.69

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18CD0017 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-05-13 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Bulacan

Based on the coordinates published with the DPWH record and NOAH file Bulacan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG STA. MARIA RIVER (BAGBAGUIN SECTION), STA. MARIA, BULACAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Sta. Maria River Phase IV (Left Side), Sta. Maria, Bulacan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-18-0034392

₱139,000.00 · FY2018

Released to Zamboanga del Norte 3rd 201 District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

409 projects · ₱21.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BALETE - SAN JOSE DIVERSION ROAD, MATAAS NA KAHOY SECTION (PHASE I), BATANGAS

Region IV-A, Region IV-A

2024₱188.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 7, BATAN

Batangas 4th DEO, Region IV-A

2024₱187.4M
Past target date (DPWH On-Going)
No sat.

MFO-1 - NAT'L. ROAD NETWORK SERVICES - WIDENING OF DAANG MAHARLIKA (TIAONG SECTION), QUEZON PROV.

Region IV-A, Region IV-A

2016₱178.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE BLDG. (TRAINING AND INSTRUCTIONAL FACILITY/MEETINGS INCENTIVES CONFERENCES FOR EDUCATION, SPORTS BUILDING (MICES) AND PRIMARY

Albay 2nd DEO, Region V

2024₱169.8M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, STO. NINO RIVER WATERWAYS ALONG ARAMAYWAN-BERONG-PTO. PRINCESA ROAD, PALAWAN

Region IV-B, Region IV-B

2025₱161.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS, PUERO PRINCESANORTH ROAD, STA. 215+005-STA. 215+365, TAYTAY, PALAWAN

Region IV-B, Region IV-B

2023₱160.2M
Reported complete (DPWH)
View all 409 projects →

4. Implementation

Contract Amount

₱79,854,170.41

Progress

Reported complete (DPWH)

Start Date

February 15, 2018

Target End

October 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanSanta MariaPoblacion
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.