Flood Control and Drainage25CB0034

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN VICENTE RIVER, ORION, BATAAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN VICENTE RIVER, ORION, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱48,005,353.06. Status: Past target date (DPWH On-Going). Contractor on record: JEK TRADING AND CONST. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along San Vicente River, Orion, Bataan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bataan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

26 projects · ₱634.2M total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANSLIDE - TERTIARY ROADS - MT SAMAT RD - K0140 + 261 - K0140 + 341, BATAAN 2ND DISTRICT

Bataan 2nd DEO, Region III

2025₱94.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FOUR (4) STOREY TWENTY (20) CLASSROOM AT BATAAN NATIONAL HIGH SCHOOL - SENIOR HIGH SCHOOL, CITY OF BALANGA, BATAAN

Bataan 2nd DEO, Region III

2024₱71.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG SAN JUAN RIVER, SAMAL, BATAAN

Bataan 1st DEO, Region III

2025₱48.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NAGBATIO CIS, MORONG, BATAAN

Bataan 3rd DEO, Region III

2025₱38.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FOUR (4) STOREY - EIGHT (8) CLASSROOM SCHOOL BUILDING, ORANI NATIONAL HIGH SCHOOL, ORANI, BATAAN

Bataan 1st DEO, Region III

2024₱31.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS- LOCAL ROADS AND BRIDGES - LOCAL ROADS- CONSTRUCTION OF NEW ROAD CURING AVENUE CONNECTING JUNCTION LAYAC-BALANGA-MARIVELES PORT ROAD AND ROMAN EXPRESSWAY

Bataan 1st DEO, Region III

2019₱29.4M
Reported complete (DPWH)
View all 26 projects →

4. Implementation

Contract Amount

₱48,005,353.06

Progress

Past target date (DPWH On-Going)

Start Date

February 17, 2025

Target End

August 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.