Construction of Flood Mitigation Structure23IL0043

Construction of Flood Control Structures in Barangay Bato 1 to 2, Maasin City, Southern Leyte

Construction of Flood Control Structures in Barangay Bato 1 to 2, Maasin City, Southern Leyte is a DPWH-tracked public work in CITY OF MAASIN (CAPITAL) (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII. Reported contract value: ₱4,881,237.85. Status: Reported complete (DPWH). Contractor on record: DAV-LEY CONST SERVICES INC FORMERLY:DAV-LEY CONST SERVICES. Figures trace to sumbong.

CITY OF MAASIN (CAPITAL) (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures in Barangay Bato 1 to 2, Maasin City, Southern Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Southern Leyte 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23IL0043 BASIC INFRASTRUCTURE PROGRAM – FLOOD MITI

₱4,881,237.85 · DAV-LEY CONSTRUCTION SERVICES

Contractor

48 projects · ₱488.9M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BARANGAY BAGONG SILANG R

Southern Leyte 1st DEO, Region VIII

2025₱29.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES CONSTRUCTION OF ROAD, BARANGAY SAN JOAQUI

Southern Leyte 1st DEO, Region VIII

2022₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BARANGAY CAGNITUAN R

Southern Leyte 1st DEO, Region VIII

2025₱29.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BOGO FLOOD CONTROL, SITIO GUTOSAN, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2021₱21.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM - ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES, CONSTRUCTION OF ROAD, PHASE II, MAMBAJAO-NASAUG-BOGO-SITIO GOTOSAN, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2023₱19.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) -BASIC INFRASTRUCTURE PROGRAM (BIP) -FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURES, STA. SOFIA, PADRE BURGOS, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2023₱19.8M
Reported complete (DPWH)
View all 48 projects →

4. Implementation

Contract Amount

₱4,881,237.85

Progress

Reported complete (DPWH)

Start Date

March 22, 2023

Target End

June 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.