Flood Control and Drainage18AE0065

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BARORO RIVER, BACNOTAN, LA UNION

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BARORO RIVER, BACNOTAN, LA UNION is a DPWH-tracked public work in La Union 1st DEO, Region I. Reported contract value: ₱56,841,564.26. Status: Reported complete (DPWH). Contractor on record: MY BUILDERS AND CONST. Figures trace to dpwh.

La Union 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Naguilian-Bagulin River, Naguilian, La Union
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033588

₱0.00 · FY2018

Released to Division of La Union (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

79 projects · ₱2.1B total · 4 flags

4. Implementation

Contract Amount

₱56,841,564.26

Progress

Reported complete (DPWH)

Start Date

April 26, 2018

Target End

March 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.