Flood Control and Drainage17DQ0003

MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION-MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL, RETAINING WALL, REVETMENT AT EAST SIDE ALONG SORO-SORO RIVER BRGY. MADUYA, CARMONA, CAVITE, 5TH LEGISLATIVE

MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION-MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL, RETAINING WALL, REVETMENT AT EAST SIDE ALONG SORO-SORO RIVER BRGY. MADUYA, CARMONA, CAVITE, 5TH LEGISLATIVE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱18,619,831.60. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures and other improvements, including removal of informal settlers along Zapote River Barangay Molino 7, Bacoor City, Cavite
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0025300

₱5,300,000.00 · FY2017

Released to Regional Office - Proper (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,619,831.60

Progress

Reported complete (DPWH)

Start Date

April 17, 2017

Target End

August 14, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.