Construction of Slope Protection Structure24BJ0006

Construction of Flood Control along Benay River, Palabotan Section, Dupax del Sur, Nueva Vizcaya

Construction of Flood Control along Benay River, Palabotan Section, Dupax del Sur, Nueva Vizcaya is a DPWH-tracked public work in DUPAX DEL SUR (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II. Reported contract value: ₱96,492,915.54. Status: Reported complete (DPWH). Contractor on record: BRG CONST. Figures trace to sumbong.

DUPAX DEL SUR (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱38,334,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Surong Centro CIS Flood Protection Works Along Tubo River, Kasibu, Nueva Vizcaya
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0005875

₱1,711,811.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010639

₱1,477,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000542

₱490,733.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004012

₱3,895,186.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004013

₱282,067.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0005876

₱151,521.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010663

₱136,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000088

₱378,582.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,492,915.54

Progress

Reported complete (DPWH)

Start Date

February 16, 2024

Target End

October 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.