Construction of Flood Mitigation Structure22K00351

Construction of Flood Control Structures at Tagoloan River (Mohon Section), Misamis Oriental

Construction of Flood Control Structures at Tagoloan River (Mohon Section), Misamis Oriental is a DPWH-tracked public work in TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱47,276,009.03. Status: Reported complete (DPWH). Contractor on record: TRIPARCO DEVELOPMENT CORP. Figures trace to sumbong.

TAGOLOAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures at Tagoloan River (Mohon Section), Misamis Oriental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002987

₱110,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002742

₱75,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003143

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003118

₱200,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005264

₱1,772,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005265

₱170,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0004831

₱47,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

357 projects · ₱29.2B total · 0 flags

Other projects by this contractor

View all 357 projects →

4. Implementation

Contract Amount

₱47,276,009.03

Progress

Reported complete (DPWH)

Start Date

November 7, 2022

Target End

July 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.