Rehabilitation / Major Repair of Flood Control Structure23HK0062

Rehabilitation of Ocoy River Control, Magatas, Sibulan, Negros Oriental

Rehabilitation of Ocoy River Control, Magatas, Sibulan, Negros Oriental is a DPWH-tracked public work in SIBULAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: PHILSOUTH BUILDERS INC FORMERLY:PHILSOUTH BUILDERS. Figures trace to sumbong.

SIBULAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Management Program - Rehabilitation of Bio-os River Control, Amlan, Negros Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Negros Oriental 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 6, 2023

Target End

October 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.