Rehabilitation / Major Repair of Flood Control Structure21BC0210

Restoration of Sicalao Flood Control, Sicalao, Lasam, Cagayan

Restoration of Sicalao Flood Control, Sicalao, Lasam, Cagayan is a DPWH-tracked public work in CAGAYAN, Region II. Reported contract value: ₱21,287,900.00. Status: Reported complete (DPWH). Contractor on record: NC RODRIGUEZ CONST. Figures trace to sumbong.

CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱8,837,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Cagayan River Basin, Brgy. Centro 9 - Brgy. Punta River Control, Aparri, Cagayan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007371

₱240,438,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012579

₱142,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005348

₱35,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012567

₱274,250,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-21-0003262

₱241,271.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-21-0008440

₱87,650.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-21-0003263

₱21,901.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-21-0008441

₱896,348.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

12 projects · ₱128.6M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - STA. FILOMENA-LANGAY BARANGAY ROAD LE

Cagayan 2nd DEO, Region II

2025₱19.4M
Reported complete (DPWH)
No sat.

CONCRETING OF BRGY. SANTA ROSA FMR, BRGY. SANTA ROSA, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2023₱14.9M
Reported complete (DPWH)
No sat.

CONCRETING OF BRGY. SANTO TOMAS FMR, BRGY. SANTO TOMAS, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2023₱14.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONIMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - GANDIA BARANGAY ROAD LEADING TO JCT.

Cagayan 2nd DEO, Region II

2024₱11.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM- CONSTRUCTION OF SOLAR WATER SYSTEMS, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2023₱9.8M
Reported complete (DPWH)
No sat.

CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-GANDIA BARANGAY ROAD LEADING TO JCT. AYAGA(ABULUG)-BALLESTEROS-APARRI ROAD CONNECTING TO AQUATIC RESOURCES, COCONUT PLANTATION AND LIVESTOCK, ALINUNU,

Cagayan 2nd DEO, Region II

2022₱9.8M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱21,287,900.00

Progress

Reported complete (DPWH)

Start Date

October 29, 2021

Target End

July 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.