Construction of Flood Mitigation Structure22OB0202

Improvement along Nangka River, Left Side Facing Upstream, from Sta. 5+524.80 to Sta. 5+893.60

Improvement along Nangka River, Left Side Facing Upstream, from Sta. 5+524.80 to Sta. 5+893.60 is a DPWH-tracked public work in CITY OF MARIKINA (METROPOLITAN MANILA), MARIKINA CITY, National Capital Region. Reported contract value: ₱91,620,467.22. Status: Reported complete (DPWH). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to sumbong.

CITY OF MARIKINA (METROPOLITAN MANILA), MARIKINA CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Maintenance and Rehabilitation of Flood Control Structure along Ilugin River, Pasig City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001726

₱202,063,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003018

₱90,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001634

₱15,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0001871

₱7,396,262.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003117

₱2,297,896,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0003214

₱1,360,967.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0001872

₱687,910.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009694

₱529,085.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0003215

₱124,316.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0005641

₱3,168,112.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱91,620,467.22

Progress

Reported complete (DPWH)

Start Date

March 17, 2022

Target End

December 11, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.