Construction of Flood Mitigation Structure24HN0162

Construction of Drainage System, Barangay Casuntingan, Mandaue City, Cebu

Construction of Drainage System, Barangay Casuntingan, Mandaue City, Cebu is a DPWH-tracked public work in MANDAUE CITY (CEBU), CEBU, Region VII. Reported contract value: ₱24,205,775.00. Status: Reported complete (DPWH). Contractor on record: ON POINT CONST AND DEVELOPMENT CORP FORMERLY:ON POINT CONST. Figures trace to sumbong.

MANDAUE CITY (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System along Malingin River, Bogo City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0020129

₱32,500,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007558

₱1,366,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0001392

₱538,511.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0018705

₱152,832.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007561

₱126,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

41 projects · ₱1.6B total · 1 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAHIGA CREEK, PHASE 3, BARANGAY S

Cebu 6th DEO, Region VII

2025₱122.4M
Past target date (DPWH On-Going)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD UNDER CANSAGA BAY BRIDGE (MANDAUE SIDE) BRGY. P

Cebu 6th DEO, Region VII

2023₱98.9M
Reported complete (DPWH)

002: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUTUANON RIVER, BARANGAY CASUNTINGAN TO BARANGAY CABANCALAN (PHASE IV), MANDAUE CITY, CEBU

Cebu 6th DEO, Region VII

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SEGMENT 2, BARANGAY HILAAN, BONTOC, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY JAGOBIAO, MANDAUE CITY, CEBU

Cebu 6th DEO, Region VII

2025₱77.1M
Past target date (DPWH On-Going)
No sat.

Construction of Flood Control Structure along Butuanon River (Downstream) Outfall, Barangay Pakna-an, Mandaue City, Cebu

MANDAUE CITY (CEBU), CEBU, Region VII

2025₱72.3M
Reported complete (DPWH)
View all 41 projects →

4. Implementation

Contract Amount

₱24,205,775.00

Progress

Reported complete (DPWH)

Start Date

July 4, 2024

Target End

April 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.