GAA 2018 OO-218BI0024

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOODMANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BONFAL EAST SECTION

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOODMANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BONFAL EAST SECTION is a DPWH-tracked public work in Nueva Vizcaya DEO, Region II. Reported contract value: ₱18,826,364.45. Status: Reported complete (DPWH). Contractor on record: JANN-NORRIS CONST AND SUPPLIES INC FORMELY: JANN-NORRIS CONST AND SUPPLIES. Figures trace to dpwh.

Nueva Vizcaya DEO, Region II
Region: Region II

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱20,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROIII-18-0013956 · · release to the district office, not itemized per project

    Possible match · score 0.78

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱18,826,364 · JANN-NORRIS CONSTRUCTION AND SUPPLIES, .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-04-22 → 2024-08-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOODMANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND  DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BONFAL EAST SECTION

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Bonfal East Section along Magat River, Bayombong, Nueva Vizcaya
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0013956

₱0.00 · FY2018

Released to Division of Nueva Ecija (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Organizational Outcome 2 Protect Lives and Proper

₱18,826,364.45 · JANN-NORRIS CONSTRUCTION AND SUPPLIES, .

Award / contract ref: 18bi0024

Contractor

B

247 projects · ₱10.9B total · 0 flags

Other projects by this contractor

No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BAYOMBONG-SOLANO BY-PASS ROAD, BAYOMBONG - SOLANO, NUEVA VIZCAYA

Region II, Region II

2019₱238.9M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0292 + 000 - K0293 + 225, K0293 + 356 - K0294 + 100, K0294 + 152 - K

Region II, Region II

2024₱196.4M
Past target date (DPWH On-Going)
No sat.

CAPITAL OUTLAY-NATIONAL BRIDGE CONST'N/REPLACEMENT PROGRAM CONST'N OF MADDIANGAT BRIDGE AND APPROACHES INCLUDING RIGHT-OF-WAY ACQUISITION ALONG BAMBANG KASIBU-QUEZON-SOLANO ROAD, NUEVA VIZCAYA

Region II, Region II

2017₱194.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG MANILA NORTH RD, - K0590+(-784) - K0593+608; K0593+637-K0595+000; K064

Region II, Region II

2024₱184.3M
Past target date (DPWH On-Going)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NAT'L ROAD SYSTEM: NETWORK DEV'T PROGRAM: ROAD WIDENING-PRIMARY ROADS ALONG DAANG MAHARLIKA (LZ),K0254+641-K0255+K249.50, K0259+899.20 - K0260+ 051.7 , K0260+072.30 - K0260+225.70, K0261+090 - K0261+242,QUIRINO LONE DISTRICT

Region II, Region II

2018₱165.2M
Reported complete (DPWH)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEV'T: ROAD WIDENING PRIMARY ROAD ALONG DAANG MAHARLIKA, K0216+886 K0219+092.70 = STA. 216+781-STA. 219+092.70, K0219+224-K0219+899 = STA. 219+138.70-STA. 219+813.70, STA. FE, NUEVA VIZCAYA

Region II, Region II

2018₱161.1M
Reported complete (DPWH)
View all 247 projects →

4. Implementation

Contract Amount

₱18,826,364.45

Progress

Reported complete (DPWH)

Start Date

February 11, 2018

Target End

July 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOODMANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BONFAL EAST SECTION.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/9d2e82f6-a106-4c9a-8768-f3cdb14190f6

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)Nueva VizcayaBayombongBonfal East
Storms whose wind field reached it
Peilou 2026Fung-Wong 2025Fengshen 2025Matmo 2025Mitag 2025
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.