Construction of Flood Mitigation Structure22MH0026

Construction of River Bank Protection/Flood Control at Hinalaan River, Kalamansig, Sultan Kudarat

Construction of River Bank Protection/Flood Control at Hinalaan River, Kalamansig, Sultan Kudarat is a DPWH-tracked public work in KALAMANSIG (SULTAN KUDARAT), SULTAN KUDARAT, Region XII. Reported contract value: ₱91,675,000.00. Status: Reported complete (DPWH). Contractor on record: JARGON CONST & SUPPLY. Figures trace to sumbong.

KALAMANSIG (SULTAN KUDARAT), SULTAN KUDARAT, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Ala River (Dansuli Section), Isulan, Sultan Kudarat
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003011

₱80,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

16 projects · ₱924.8M total · 0 flags

4. Implementation

Contract Amount

₱91,675,000.00

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

January 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.