Flood Control and Drainage18PC0047

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG CLAVERIA(CABICUNGAN) RIVER, BRGY STA. FILOMENA, CALANASAN, APAYAO

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG CLAVERIA(CABICUNGAN) RIVER, BRGY STA. FILOMENA, CALANASAN, APAYAO is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,347,563.76. Status: Reported complete (DPWH). Contractor on record: GKA ENGINEERING AND CONST. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱10,000

    Probable match · score 0.92

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROVI-18-0003102 · ₱27,459,000 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18PC0047 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-03-16 → 2018-03-16

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Apayao

Based on the coordinates published with the DPWH record and NOAH file Apayao.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG CLAVERIA(CABICUNGAN) RIVER, BRGY STA. FILOMENA, CALANASAN, APAYAO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Control Structures along Claveria (Cabicungan) River, Brgy. Sta. Filomena, Calanasan, Apayao
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-18-0003102

₱27,459,000.00 · FY2018

Released to Apayao 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

58 projects · ₱595.3M total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTI-PURPOSE/ FACILITIES, CONSTRUCTION (COMPLETION) OF DPWH BUILDING APAYAO 1ST DISTRICT ENGINEERING OFFICE, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2023₱38.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, ABBUT-CONNER RD-K0548+630-K0548+702

Apayao 1st DEO, Cordillera Administrative Region

2025₱27.2M
Past target date (DPWH On-Going)
No sat.

Construction of Barren River (Downstream) Flood Control along Chico River Basin, Sta. 37 + 414 - Sta. 37 + 664 (R/S), Barangay Paddaoan, Conner, Apayao

CONNER (APAYAO), APAYAO, Cordillera Administrative Region

2023₱24.5M
Reported complete (DPWH)
No sat.

PACKAGE I: ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE (SECONDARY ROADS) KABUGAO-PUDTOL-LUNA-CAGAYAN ROAD, 1.) K0623+446-K0624+112, 2.) K0626+(-072)-K0626+(-006), 3.) K0626+278-K0626+331(RS),

Apayao 2nd DEO, Cordillera Administrative Region

2019₱21.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, CONNER-KABUGAO RD- K0581+090-K0581+319

Apayao 1st DEO, Cordillera Administrative Region

2023₱19.6M
Reported complete (DPWH)
No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 1: CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND: CONSTRUCTION OF 2STY6CL WITH LABORATORY, CONNER NATIONAL HS, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱19.4M
Past target date (DPWH On-Going)
View all 58 projects →

4. Implementation

Contract Amount

₱9,347,563.76

Progress

Reported complete (DPWH)

Start Date

April 26, 2018

Target End

November 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Cordillera Administrative Region (CAR)ApayaoCalanasan
Storms whose wind field reached it
Noul 2026Fung-Wong 2025Matmo 2025Ragasa 2025Mitag 2025
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.